CAGLIARI SOLAR 2018
COUNTRY
Italy
CITY
Macchiareddu (CA)
YEAR
2024-2025
CUSTOMER
Cagliari Solar 2018
DESCRIPTION
CR Project Service’s expertise in the renewable energy sector guided the execution of the “Cagliari Solar 2018” project, a strategic intervention serving a photovoltaic plant with a total nominal capacity of 44 MWp.
Delivered on a turnkey basis, the project encompassed the full construction of a new 220/30 kV user electrical substation, covering both civil works and the installation of electromechanical infrastructure. To complete the facility, CR Project Service managed the design and installation of the corresponding MV-HV connecting cable line, ensuring seamless connection to the national transmission grid operated by TERNA.
Integrating the best technologies within our group was essential to the success of the project: for the supply of critical substation equipment, we relied on the support and high-performance products of our sister company, CR Technology Systems S.p.A.